Overview
The Armys Engine Process Analysis Services
(EPAS) project funded by the Rotary Wing Aircraft Sustainment
Program (RWASP) is now paying dividends in three key areas:
(1) Overhaul Cycle Time Reduction: 342 to 146 days and going
down; (2) Improved
Engine Life: 240 to 1080 hours on the wing; and (3)
Increased
Deliveries: 8 to 75 engine equivalents per month. The
estimated payback to the Army from the EPAS project is $140M
over the next ten years.
The EPAS Team (AMCOM/CCAD/AT&T/KBSI), using
the Air Force Lean Value
Chain and KCHR
technologies, has affected major improvements without major
equipment or facilities investments and moderate increases
in CCAD manpower. A summary of how this was accomplished is
provided in the following list.
|